Advait Energy Transitions secures 180 MW/360 MWh BESS EPC project in Gujarat

Share

Advait Energy Transitions Ltd (formerly Advait Infratech Ltd) announced today that it has received an order from Gujarat BESS Pvt Ltd to set up a 180 MW/360 MWh (AC side) battery energy storage system (BESS) project on an EPC basis. The project will be located in Sanand city, Gujarat.

Advait Energy’s scope of work includes the supply, erection, testing, and commissioning of the BESS.

The project is scheduled for mechanical completion by November 30, 2025, with final charging planned by December 23, 2025.

The total project value is INR 7.43 crore, inclusive of taxes.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

REC posts highest-ever annual profit of INR 15,713 crore
08 May 2025 REC Ltd, a non-banking finance company focused on the power sector, has reported a record net profit of INR 15,713 crore for FY 2024-25, marking a 12%...