India’s expanding renewable energy base and clean power can play a central role in supporting the next phase of data center growth, supported by smarter power sourcing, stronger grid readiness and coordinated policy action to ensure reliable and sustainable energy at scale, says a new report by Deloitte Asia Pacific.
Launched at the AI Summit, the report titled “Powering Asia Pacific’s Data Centre Boom report” highlights that as the Asia Pacific region emerges as the next major global data center hub, India has a strong opportunity to position itself at the forefront, provided critical enablers are aligned. Rapid data center expansion is creating significant economic value while also placing new pressure on energy systems in transition, making it essential to balance growth with reliable and sustainable power.
“Asia Pacific is at a tipping point,” said Will Symons, Deloitte Asia Pacific Sustainability Leader. “AI, cloud and digital connectivity is surging, driving massive new investments in energy-intensive data centers. Across the region electricity grids are already under pressure to decarbonize and maintain affordability, resilience and security. Taking a power-first approach with clean energy is critical to power new data centers, accelerate decarbonization and underpin continued economic growth.”
“India has a rare structural opportunity to rise as one of the world’s leading data centre hubs, powered by its cost competitiveness, deep talent and rapidly expanding renewable energy base,” said Debasish Mishra, Chief Growth Officer (CGO), Deloitte South Asia. “The defining moment will be how swiftly power availability and transmission readiness scale with the country’s digital ambition. With the right alignment of policy, grid infrastructure and renewable deployment, India can build AI infrastructure that is globally competitive, sustainable and future ready, and position itself at the heart of the next era of digital growth.”
The report identifies the following key challenges in powering AI data centre in India:
- New data centres are growing fast, but power generation is not keeping up, creating an energy supply gap.
- Grid stability limitations and constrained substation capacity in high growth corridors
- Longer development timelines for transmission upgrades compared to renewable generation projects
- Regulatory differences across states in renewable banking, tariffs and policy incentives
- Lack of a unified national framework to support renewable integration for data centres
To address these challenges, the report recommends:
- Accelerate renewable integration through solar-wind hybrid models with storage to ensure reliability for high-density AI workloads
- Expand long-term green PPAs, group captive structures and captive renewable installations to provide tariff certainty
- Upgrade transmission networks and expand high-capacity substations near growth clusters
- Develop power-ready dedicated Data Centre Economic Zones with pre-built substations and standardised connection timelines
- Standardise state-level renewable banking policies to provide predictable round-the-clock clean power portfolios
- Leverage AI to run non-urgent computing tasks at times when clean and low-cost electricity is available
- Incentivise decentralised renewable models including co-located solar and storage infrastructure in emerging corridors
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.






By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.