Juniper Green Energy has fully commissioned its 100 MWh merchant battery energy storage system (BESS) project at Bikaner, Rajasthan, through its subsidiary Juniper Green Cosmic. This commissioning marks its first operational merchant BESS.
The developer said that the 100 MWh capacity has successfully completed trial operations and received approval from the Northern Regional Load Despatch Centre (NRLDC). Commercial operations for the entire project started on January 23rd, 2026.
The project is now fully commissioned at 100 MWh capacity and has become one of the largest operating BESS in India, offering significant potential for merchant revenue streams including peak arbitrage, grid balancing services, and ancillary market participation.
Juniper Green Energy has partnered with global renewable major, Envision Energy, for the supply & installation of energy storage systems at its Bikaner plant.
“With India’s first merchant BESS now fully commissioned, Juniper Green Energy reaffirms its leadership in energy storage innovation. This milestone unlocks new revenue streams while bolstering grid stability and accelerating our renewable energy mission,” said Ankush Malik, CEO, Juniper Green Energy.
In parallel, Juniper Green Energy has already installed 400 MWh of BESS capacity at Fatehgarh, Rajasthan, which is expected to be commissioned by Q1 2026, further strengthening the company’s storage portfolio and long-term growth visibility.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.






By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.