L&T Construction has commissioned 185 MW of grid-connected solar capacity coupled with a 254 MWh battery energy storage system at Kajra in Bihar’s Lakhisarai district, marking India’s largest commissioned solar-plus-BESS project to date.
Developed for Bihar State Power Generation Co. Ltd (BSPGCL), the project was executed by L&T on an EPC basis. The tender was issued in December 2023, with L&T awarded the EPC contract along with ten years of operations and maintenance in June 2024.
The co-located BESS will enable storage of solar energy during low-demand period and discharge when the demand peaks. In addition, it will help smoothening the fluctuations in generation, frequency regulation and voltage support. It comes with black start capability to the grid that will facilitate quick re-energization after an outage.
The project is the second large-scale BESS project to be commissioned in India, following an earlier installation in Chhattisgarh.
Hithium supplied 82 containerized BESS units using lithium iron phosphate (LFP) chemistry and liquid-cooling technology, designed to ensure safety, efficiency, and reliable performance under high thermal conditions.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.






By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.