SJVN secures 2.4 GW pumped storage project in Mizoram

Share

SJVN has received a Letter of Intent for allotment of a 2.4 GW pumped storage project from the state government of Mizoram. The pumped storage project has been proposed across Darzo Nallah, a tributary of Tuipui river.

The estimated cost of the project on completion is INR 13,947.50 crores including IDC [interest during construction) and financing costs at April 2023 price level.

This is SJVN’s first project in the state of Mizoram. The pumped storage project is on-stream closed-loop type. It comprises eight units of 300 MW each.

“The annual energy generation with 95% plant availability shall be 4,993.20 MU. The annual input energy required for pumping water to the upper reservoir has been estimated to be 6,331.66 MU with 95% plant availability,” stated SJVN.

The project completion period is 72 months. The agreement shall be signed within three months between SJVN and the Government of Mizoram.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

Gautam Solar unveils n-type TOPCon rectangular bifacial panel with 640 Wp output
21 April 2025 Gautam Solar has introduced n-type TOPCon rectangular bifacial panels with power output ranging from 620 Wp to 640 Wp and efficiency ranging from 22.9...