SJVN tenders BoS package for 125 MW solar in Bihar

Share

SJVN Green Energy has tendered the balance of system (BoS) package for a 125 MW grid-connected solar plant at Jamui, Bihar.

The prospective contractor’s scope of work includes design, engineering, supply, construction, erection, testing, commissioning and three years of comprehensive operation and maintenance of the solar plant, excluding the supply of PV modules.

“PV modules shall be supplied to the BOS contractor by SJVN Green Energy,” reads the tender document.

EPC completion period is 465 days from the award of contract.

SJVN Green Energy has already signed a power purchase agreement with BREDA.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

Juniper Green raises $1 billion in debt financing to expand its clean energy portfolio
10 February 2025 Juniper Green Energy has secured $1 billion in phased debt financing to support the development of wind-solar hybrid and firm & dispatchable renew...