Adani Green targets over 10 GWh of installed BESS capacity by FY 2027-end
Adani Green Energy’s operational renewable energy (RE) capacity increased by 24% year on year (YoY) to 20,763 MW in H1 FY 2027, with the addition of 4,083 MW of greenfield capacity.
The company operationalized 2,957 MW of solar power plants, including 2,568 MW in Khavda, Gujarat, and 389 MW in Rajasthan. It also commissioned 805 MW of wind power capacity, comprising 666 MW in Khavda and 139 MW in Mundra, Gujarat, along with 321 MW of hybrid power capacity in Khavda.
During Q2 FY 2027, Adani Green Energy operationalized 3,081 MWh of battery energy storage system (BESS) capacity in Khavda. The deployment brings its total installed BESS capacity to 6,632 MWh as of H1 FY 2027. The company expects to surpass 10 GWh of installed BESS capacity by the end of FY 2027.
The company’s energy sales increased by 32% YoY to 25,747 million units in H1 FY 2027, supported by capacity additions. Its solar portfolio recorded a capacity utilization factor (CUF) of 22.9%, with plant availability at 99.3%.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: [email protected].
Please login to comment