India likely to commission 45-50 GWh of BESS capacity across fiscals 2027 and 2028: Crisil
India is likely to commission 45-50 GWh of battery energy storage system (BESS) capacity in fiscals 2027 and 2028, compared with just around 1 GWh commissioned as of the end of fiscal 2026, according to Crisil Ratings. The expansion is supported by a strong project pipeline and continued policy support.
Around 50-55 GWh of BESS capacity is currently scheduled for commissioning during the two fiscals. However, around 8-9 GWh of the awarded capacity faces a higher risk of delay, mainly because of weak project returns and limited implementation experience among some developers, Crisil said.
The analysis covers bids awarded between fiscals 2024 and 2026 across nearly 100 renewable energy developers.
The government has accelerated storage-linked auctions to support the integration of a larger share of renewable energy into the national power grid. Projects incorporating BESS accounted for nearly 40% of total auctioned capacity in fiscal 2026, up sharply from about 5% in fiscals 2024 and 2025.
Of the 50-55 GWh of BESS capacity scheduled for commissioning across fiscals 2027 and 2028, around 40 GWh has been awarded through government-led auctions, where distribution utilities are the offtakers. The remaining 10-15 GWh is expected to serve commercial and industrial consumers directly or be deployed in the merchant market.
“Nearly 21% of the under-construction BESS capacity, equivalent to about 12 GWh, faces weak return potential which may lead to some delays in commissioning. The risk has emerged because battery prices have hardened in 2026, while tariffs bid out for these projects were relatively low,” says Manish Gupta, Senior Director and Deputy Chief Ratings Officer. “Developers typically procure batteries about a year after securing project bids. Consequently, most projects awarded in 2025 are now exposed to higher battery prices, which have rebounded from the lows witnessed in 2025. As the battery prices were consistently coming down till 2025, developers appeared to have bid aggressively on the assumption that prices would continue their downward trajectory.”
Battery prices have increased, and at prevailing levels, project returns may be insufficient to achieve the typical target internal rate of return (IRR) of 12%-14%. Consequently, developers may defer implementation in anticipation of more favourable battery pricing. [With a sample tariff of INR 2.2-2.5 lakh per MW per month, and battery prices of $55-65/kWh, a project is expected to generate IRR of 12-14%.]
“Approximately 8-9 GWh out of this 12 GWh of the planned capacity is exposed to an additional challenge: limited implementation experience among project sponsors,” says Ankit Hakhu, Director, Crisil Ratings. “While BESS projects typically face relatively lower land acquisition and connectivity-related challenges compared to conventional renewable energy projects, equipment procurement remains a key risk given the sector’s continued dependence on overseas suppliers for batteries and other critical components. Developers with limited scale or procurement track records may face challenges in securing equipment on competitive terms, which could adversely impact IRRs. Consequently, any increase in procurement costs, coupled with execution-related challenges, could moderate IRRs and/or result in delays in project commissioning. Early signs of these pressures are already evident across parts of the under-construction pipeline with projects getting stranded.”
That said, most awarded capacity remains either in the development stage or in the early phases of construction. The sector continues to depend heavily on overseas suppliers for batteries and other critical components. While long-term battery demand is underpinned by strong structural drivers, the potential impact of geopolitical developments and disruptions to global supply chains warrants close monitoring.
The growing need for energy storage stems from the rising share of solar and wind, which accounted for 39% of India’s installed power generation capacity and around 15% of electricity generation in fiscal 2026. As of the end of fiscal 2026, India’s total installed power capacity stood at 533 GW, of which renewable energy (RE) accounted for around 206 GW.
However, by nature, the RE generation is intermittent, which has increased the need for firm and peak-hour power supply and thus energy storage solutions, particularly BESS. The requirement is especially acute for solar projects because electricity demand typically peaks in the evening, when solar generation is negligible. BESS can address this mismatch by storing surplus solar power during periods of high generation and supplying it during periods of elevated demand.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: [email protected].
Please login to comment