ACME Solar commissions additional 66.68 MW of solar capacity at hybrid project in Rajasthan

ACME Solar’s hybrid project in Bikarner benefits from a power purchase agreement (PPA) with NTPC at a tariff of INR 3.36 per kWh.
Acme Solar

ACME Solar has commissioned an additional 66.68 MW of solar capacity at its hybrid renewable energy project in Bikaner district, Rajasthan.

The project, located at Village Kelan in Chhatargarh tehsil, has been commissioned through the company’s subsidiary, ACME Renewtech, on Nov. 2, 2026. The commercial operation date (COD) for the newly commissioned capacity is Nov. 4, 2026.

The commissioned capacity forms part of ACME Solar’s hybrid renewable energy project combining 300 MW of solar capacity with 100 MW of wind capacity.

With this commissioning, ACME Renewtech has achieved a cumulative commissioned solar capacity of 200.04 MW out of the project’s planned 300 MW solar component.

The project is backed by a power purchase agreement (PPA) with NTPC at a tariff of INR 3.36 per kWh. ACME Solar expects to progressively commission the entire 300 MW solar component by the end of Q3 FY27.

The addition of wind capacity to the hybrid project is expected to complement solar generation and provide a more diversified renewable energy generation profile.

Following this commissioning, ACME Solar’s total operational capacity has increased to approximately 3,190 MW.